@RISK: Using @RISK with Projects in Progress
There are a few approaches to choose from: 1. Change Date Range - Requires @RISK 6.0 or newer 2. A practical method is to place distributions on Remaining Duration instead of Duration. 3. You can remove distributions from completed tasks and enter the actual finish or actual duration.